02:02 Wed 16 Dec 2020
Rio Tinto - Development pathway for Oyu Tolgoi underground

Rio Tinto confirms development capital and timeline for Oyu Tolgoi underground
Rio Tinto today unveiled a pathway for the ongoing development of the underground project at Oyu Tolgoi in
Rio Tinto and its partners, the Government of
At peak production, Oyu Tolgoi is expected to operate in the first quartile of the copper cash cost curve[1] and by 2030 is expected to be the fourth largest copper mine in the world.
Oyu Tolgoi is expected to produce 480,000 tonnes[2] of copper per year on average from 2028 to 2036 from the open pit and underground, compared with 146,300 tonnes[3] in 2019 from the open pit. The underground Ore Reserve has an average copper grade of 1.52 per cent, which is more than three times higher than the open pit Ore Reserve, and contains 0.31 grammes per tonne of gold.[4] The size and quality of this Tier 1 asset provides additional expansion options, which could see production sustained for many decades.
Definitive estimate for Panel 0 complete
Rio Tinto has completed the definitive estimate work for Panel 0 of the Oyu Tolgoi Underground Project, confirming a revised budget of
Panel 1 and Panel 2 (which are required to support the ramp-up to 95,000 tonnes of ore per day) are currently subject to further studies, with initial recommendations expected by mid-2021. These studies will also consider options and associated costs to recover the copper contained within the pillars added to the mine design of Panel 0.
Government approvals
On
The definitive estimate, the mine design and the budget uplift for the underground project need to be approved by the board of Oyu Tolgoi LLC, which is jointly owned by Erdenes Oyu Tolgoi LLC on behalf of the Government of
Power
The Government of
The Government has committed to provide stable, reliable, and uninterrupted power to Oyu Tolgoi from a domestic power plant, which will be owned and funded by the Mongolian Government. Until this domestic power solution is in place, existing power supply arrangements will be extended by the Government, on terms that are acceptable to Oyu Tolgoi, to ensure that the mine has a continuous and competitive power supply. The parties have agreed that key milestones include
Funding
In
Rio Tinto has, through TRQ, made significant equity contributions to fund Oyu Tolgoi to date and is providing completion support undertaking in respect of the
Economic and social contribution
More than
Oyu Tolgoi has a workforce of over 12,000, of which 95 per cent is Mongolian. It has paid more than
The Oyu Tolgoi Development Support fund invests over
The "Made in
Oyu Tolgoi is amongst the safest operations and is also one of the most water-efficient mines in the world, with average water use of 0.35 cubic metres of water per tonne (m3/t ) of ore processed in 2019 (global average 1.22m3/t). The water used by Oyu Tolgoi comes from a deep and saline aquifer and has no impact on drinkable water in the region. In 2019, water used by Oyu Tolgoi was continuously recycled at an average rate of 87.5 per cent.
Ore Reserves and Mineral Resources
The completion of the definitive estimate has resulted in some non-material changes to the Ore Reserves and Mineral Resources that were reported in a release to the Australian Securities Exchange on
Ore Reserves are presented in this release on a 100 per cent basis. Rio Tinto's ownership share is 33.5% of
Table A: Changes to the Hugo Dummett North and
| ||||||||||
| Probable Ore Reserves | Average Mill Recovery | Recoverable Metal | |||||||
| Tonnes (Mt) | Cu (%) | Au (g/t) | Ag (g/t) | Cu (%) | Au (%) | Ag (%) | Cu (Mt) | Au (M oz) | Ag (M oz) |
Reserves at | 400 | 1.51 | 0.29 | 3.11 | 93 | 79 | 80 | 5.6 | 2.99 | 32 |
Material added | 12 | 1.72 | 0.23 | 3.72 | 93 | 81 | 85 | 0.18 | 0.07 | 1.17 |
Reserves at | 412 | 1.52 | 0.29 | 3.13 | 93 | 79 | 80 | 5.78 | 3.06 | 33.17 |
| | |||||||||
| Probable Ore Reserves | Average Mill Recovery | Recoverable Metal | |||||||
| Tonnes (Mt) | Cu (%) | Au (g/t) | Ag (g/t) | Cu (%) | Au (%) | Ag (%) | Cu (Mt) | Au (M oz) | Ag (M oz) |
Reserves at | 40 | 1.54 | 0.53 | 3.63 | 92 | 81 | 83 | 0.57 | 0.55 | 3.84 |
Material removed | -2 | 1.12 | 0.33 | 2.41 | 92 | 81 | 82 | -0.02 | -0.01 | -0.1 |
Reserves at | 38 | 1.56 | 0.54 | 3.68 | 92 | 81 | 83 | 0.55 | 0.54 | 3.73 |
Table B: Changes to the Hugo Dummett North and
| ||||||||||||||||
| Measured Mineral Resources | Indicated Mineral Resources | Inferred Mineral Resources | Total Mineral Resources | ||||||||||||
| Tonnes | Cu | Au | Ag | Tonnes | Cu | Au | Ag | Tonnes | Cu | Au | Ag | Tonnes | Cu | Au | Ag |
Resources at | 58 | 1.86 | 0.48 | 4.21 | 401 | 1.34 | 0.34 | 3.14 | 765 | 0.80 | 0.28 | 2.40 | 1,224 | 1.03 | 0.31 | 2.73 |
Material removed | -0.25 | 2.58 | 0.11 | 7.05 | -3.99 | 1.27 | 0.36 | 3.87 | -0.11 | 0.33 | 0.08 | 0.37 | -4.35 | 1.32 | 0.34 | 3.96 |
Resources at | 58 | 1.86 | 0.49 | 4.20 | 398 | 1.34 | 0.34 | 3.14 | 765 | 0.80 | 0.28 | 2.40 | 1,220 | 1.03 | 0.31 | 2.73 |
| ||||||||||||||||
| Measured Mineral Resources | Indicated Mineral Resources | Inferred Mineral Resources | Total Mineral Resources | ||||||||||||
| Tonnes | Cu | Au | Ag | Tonnes | Cu | Au | Ag | Tonnes | Cu | Au | Ag | Tonnes | Cu | Au | Ag |
Resources at |
|
|
|
| 87 | 1.59 | 0.54 | 4.11 | 167 | 1.02 | 0.36 | 2.78 | 254 | 1.21 | 0.42 | 3.24 |
Material removed |
|
|
|
| -0.62 | 1.26 | 0.24 | 2.89 |
|
|
|
| -0.62 | 1.26 | 0.24 | 2.89 |
Resources at |
|
|
|
| 87 | 1.59 | 0.54 | 4.12 | 167 | 1.02 | 0.36 | 2.78 | 253 | 1.21 | 0.42 | 3.24 |
TABLE OF KEY METRICS | |
Ore Reserve tonnes and grade (UG)[7] | |
Ore Reserve tonnes and grade (OP)[8] | |
First sustainable production (year) | 2022 |
Peak production average from 2028-2036 (copper and gold)[9] | 480kt Cu and 340koz Au per year |
Total capex | |
Competent Persons Statement
The information in this release that relates to Ore Reserves is based on information compiled by
The information in this release that relates to Mineral Resources is based on information compiled by Oyunjargal Dendev, a Competent Person who is a Member of The Australasian Institute of Mining and Metallurgy. Oyunjargal Dendev is a full-time employee of Oyu Tolgoi LLC. Oyunjargal Dendev has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Oyunjargal Dendev consents to the inclusion in the release of the matters based on the information that he has prepared in the form and context in which it appears.
Note to editors
Oyu Tolgoi is jointly owned by the Government of
The open-pit mine was completed in less than 24 months and production started in 2013. Since then, more than 240 million tonnes of ore have been milled, with over one million tonnes of copper in concentrate sold.
Contacts
Follow @RioTinto on Twitter
Media Relations, M +44 7920 503 600
T +44 20 7781 1623 M +44 7787 597 493
Media Relations, T +1 514 608 4429
Media Relations, T +65 6679 9290 M +65 9722 6028
| Media Relations, T +61 3 9283 3088 M +61 447 028 913
T +61 3 9283 3087 M +61 433 525 739
T +61 8 6211 6013 M +61 436 653 412 |
Investor Relations,
T +44 20 7781 2051 M +44 7920 010 978
|
Investor Relations, T +61 3 9283 3063 M +61 409 210 462
Amar Jambaa T +61 3 9283 3627 |
Group Company Secretary Rio Tinto plc T +44 20 7781 2000 Registered in No. 719885 |
Joint Company Secretary Rio Tinto Limited Level 7, T +61 3 9283 3333 Registered in ABN 96 004 458 404 |
This announcement is authorised for release to the market by Rio Tinto's Group Company Secretary.
[1] WoodMackenzie copper equivalent cash cost curve (Q3 2020)
[2] This production target (stated as recovered metal) for the Oyu Tolgoi underground and open pit mines is underpinned 22 per cent by Proved Ore Reserves and 78 per cent by Probable Ore Reserves for the years 2028-2036, which have been scheduled from current mine designs by Competent Persons in accordance with the requirements of the Australasian Code for Reporting of Exploration Results, Minerals Resources and Ore Reserves, 2012 Edition (the JORC code).
[3] Rio Tinto Fourth Quarter Operations Review, published
[4] The Ore Reserves for
[5] This estimate is at a better than feasibility study level of accuracy.
[6] The definitive estimate assumes restrictions in 2021 that are no more stringent than those experienced in
COVID-19 constraints continue beyond 2021, or should the COVID-19 situation escalate further in 2021 leading to tougher restrictions, additional costs and schedule impacts will arise.
[7] See Table A.
[8] Oyu Tolgoi Ore Reserves include Proved and Probable Ore Reserves for the
[9] This production target (stated as recovered metal) for the Oyu Tolgoi underground and open pit mines is underpinned 22 per cent by Proved Ore Reserves and 78 per cent by Probable Ore Reserves for the years 2028-2036, which have been scheduled from current mine designs by Competent Persons in accordance with the requirements of the JORC code.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
NO INVESTMENT ADVICE
The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...
FOR OUR FULL DISCLAIMER CLICK HERE