logo-loader
Perseus Mining Ltd

Perseus Mining meets quarterly guidance for gold production, Yaouré mine development ongoing

The company is on track to reach its target of about 500,000 ounces of gold production a year with an AISC of US$850 by 2022.

1548119616_757z468_1540767624_Perseus-gold-pour.jpg
A gold pour at one of Perseus Mining’s two operating West African mines

Perseus Mining Limited (ASX:PRU) has met quarterly guidance for gold production at its Edikan and Sissingué mines in West Africa.

The company is also advancing development of its Yaouré Gold Project in Cote d’Ivoire with construction expected to start in the March quarter 2019 and first gold scheduled in late 2020.

Cashflow from operations during the December quarter amounted to $18.8 million and Perseus had $92 million cash and bullion on hand at the end of 2018.

Bank debt was reduced during the quarter by US$3.9 million to US$48.5 million, leaving the company in a net position of $23.3 million.  

 

Quarterly production comprised 68,078 ounces of gold at an average all-in sustaining cost (AISC) of $1,052.

Production at Edikan in Ghana was 50,141 ounces at an AISC of $1,151 while the remaining 17,937 ounces came from Sissingué at an AISC of $776.

Gold sales for the quarter totalled 66,705 ounces at an average sales price of $1,250 an ounce.

Total production for the December 2018 half year and full 2018 calendar year of 140,555 and 288,463 ounces, respectively, was in line with market guidance.

The AISC achieved over the calendar year was $994 an ounce, within the guidance of $950-$1,100.

Monthly balance of cash and bullion and interest-bearing liabilities

 

READ: Perseus Mining awards engineering and supply contract for Yaouré Gold Project

Both gold mines experienced heavier-than-usual rainfall during the quarter which impacted on costs and production compared to previous periods.

Costs at Edikan were affected by Perseus’ decision in August to transition from two mining contractors to just one.

One-off demobilisation costs were recorded in the quarter, but the company expects the revised life-of-mine plan being implemented this month to deliver overall cost reductions.

READ: Perseus Mining auditions project for multi-country mines strategy

While the rain abated at Sissingué early in the quarter, pit access for grade control and mining was progressively restored but not in the sequence originally set out in the mine plan.

This led to a reduction in the head grade of processed ore as lower-grade material was mined instead of inaccessible higher-grade ore from the pit bottom.

Since quarter-end access to all areas of the mine have been restored and production has returned to above budgeted levels.

 

READ: Perseus Mining new discovery at Edikan bodes well for mine life extension

Perseus continued development of its Yaouré project during the quarter, with an exploitation permit application advancing through required government approvals.

The company expects the Cote d’Ivoire government to grant the permit soon and has confirmed that a tax exoneration status will apply to the project company.

A front-end engineering and design (FEED) study was completed early in the quarter, estimating a total capital cost of US$264 million for Yaouré, plus-minus 10%.

This figure is within 0.5% of the definitive feasibility study estimate and assumes the process plant will be developed under an engineering, procurement and construction-style contract.

READ: Perseus Mining leveraged to high-grade gold results from West African project

Earlier this month Perseus issued a notice of award for engineering and supply contracts at Yaouré to Lycopodium Limited (ASX:LYL).

The contracts are subject to finalisation of formal contract documentation, full project funding and granting of the exploitation permit.

Lycopodium was contracted by Perseus to develop the Sissingué mine which commissioned in early 2018 and came online ahead of time and on budget.

Preliminary site works at Yaouré will begin in the March quarter managed by Perseus’ in-house development team and funded from existing cash reserves.

Full-scale construction of the mine and associated infrastructure is expected to start shortly after, with first gold anticipated for December 2020.

Quick facts: Perseus Mining Ltd

Price: $0.81

Market: ASX
Market Cap: $946.06 m
Follow

Add related topics to MyProactive

Create your account: sign up and get ahead on news and events

NO INVESTMENT ADVICE

The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is...

In exchange for publishing services rendered by the Company on behalf of Perseus Mining Ltd named herein, including the promotion by the Company of Perseus Mining Ltd in any Content on the Site, the Company receives...

FOR OUR FULL DISCLAIMER CLICK HERE

Watch

Perseus Mining highlights golden milestones for June quarter

Perseus Mining managing director and CEO Jeff Quartermaine speaks to Proactive Investors about the latest quarterly update with gold production reaching more than 64,000 ounces. “This has meant half yearly production figures of 131,269 ounces are well above the guidance range we gave to...

on 17/7/19

4 min read